星期三, 26 2 月, 2025
Home PV News Europe Portugal set to start up Europe's largest floating solar park

Portugal set to start up Europe’s largest floating solar park

Source:REUTERS

ALQUEVA, Portugal, May 9 (Reuters) – Two tugboats have moved a vast array of 12,000 solar panels, the size of four soccer pitches, to their mooring on Portugal’s Alqueva reservoir in preparation to start up Europe’s largest floating solar park in July.
Built by the country’s main utility EDP (EDP.LS) on Western Europe’s biggest artificial lake, the shiny floating island is part of Portugal’s plan to cut reliance on imported fossil fuels whose prices have surged since Russia’s invasion of Ukraine.
Blessed by long hours of sunshine and Atlantic winds, Portugal has accelerated its shift to renewables. But even though Portugal uses almost no Russian hydrocarbons, its gas-fired power plants still feel the squeeze of rising fuel prices.
Miguel Patena, EDP group director in charge of the solar project, said on Thursday when the tugboats moved the panels into position that electricity produced from the floating park, with installed capacity of 5 megawatts (MW), would cost a third of that produced from a gas-fired plant.
The panels on the Alqueva reservoir, which is used to generate hydropower, would produce 7.5 gigawatt/hours (GWh) of electricity a year, and would be complemented by lithium batteries to store 2 GWh.
The solar panels will supply 1,500 families with power or a third of the needs of the nearby towns of Moura and Portel.

“This project is the biggest floating solar park in a hydro dam in Europe, it is a very good benchmark,” Patena said.
Solar panels mounted on pontoons on lakes or at sea have been installed in range of places from California to polluted industrial ponds in China, in the fight to cut CO2 emissions.
Floating panels do not require valuable real estate and those on reservoirs used for hydropower are particularly cost effective as they can hook up to existing links to the power grid. Excess power generated on sunny days can pump water up into the lake to be stored for use on cloudy days or at night.
EDP executive board member Ana Paula Marques said the war in Ukraine showed the need to accelerate the shift to renewables
She said the Alqueva project was part of EDP’s strategy “to go 100% green by 2030”, with hydropower and other renewables now accounting for 78% of EDP’s 25.6 GW of installed capacity.
In 2017, EDP installed a pilot floating solar project with 840 panels on the Alto Rabagao dam, the first in Europe to test how hydro and solar power could complement each other.
EDP already has plans to expand the Alqueva project. It secured the right in April to build a second floating farm with 70 MW installed capacity.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Tongwei and R.Power S.A. signed 100MW PV agreement

In February 2025, during the Polish Photovoltaic Exhibition, Tongwei Co., Ltd. and R.Power S.A. officially signed a 100MW photovoltaic project cooperation agreement. This agreement...

Talon PV gains licence for TOPCon solar cell patents from First Solar

US-based manufacturer of crystalline silicon photovoltaic solar cells, Talon PV, has secured a licence for tunnel oxide passivated contact (TOPCon) cell manufacturing patents from...

Solar module prices are expected to increase in the next six months

Solar module prices are expected to increase significantly from current levels in the next six months, according to Yana Hryshko, head of Solar Supply...

NTU Singapore and Trinasolar Collaborate on AI-Powered Smart Energy Storage

Nanyang Technological University, Singapore (NTU Singapore) has partnered with Trinasolar, a global provider of photovoltaic (PV) and energy storage solutions, to develop advanced smart...