星期四, 21 11 月, 2024
Home PV Project Developer’s Plea for Extending Commissioning Dates for 140 MW of Solar Projects...

Developer’s Plea for Extending Commissioning Dates for 140 MW of Solar Projects Rejected

The Commission noted that NTPC was entitled to liquidated damages for the delay in commissioning of the projects

Source:MERCOM

The Central Electricity Regulatory Commission (CERC), in a recent order, rejected the request of a solar developer for extension of the scheduled commissioning dates of two solar projects of 70 MW each at the Bhadla Solar Park in Rajasthan.
The Commission added that NTPC was entitled to liquidated damages for the delay in commissioning of two solar projects of 70 MW each.
Solaire Solar Urja had filed a petition with CERC seeking an extension of the scheduled commissioning dates for two solar projects of 70 MW and seeking a refund of ?70.6 million (~$950,701) as the liquidated damages collected by NTPC for the delay in commencement of the supply of power from the projects.
Background
Solaire Surya Urja is a wholly-owned subsidiary of Solairedirect Energy India, which in turn is a step-down subsidiary of ENGIE.
Solaire Surya Urja has two solar power projects of 70 MW each at the Bhadla Solar Park in the Jodhpur district of Rajasthan developed under the National Solar Mission Phase-II, Batch-II, Tranche-I, state-specific bundling program.
The Government of India appointed NTPC to purchase and sell solar power under the program.
On May 21, 2015, NTPC issued the request for selection. On January 18, 2016, Solaire was selected as the successful bidder for setting up two solar projects of 70 MW each at the Bhadla Solar Park.
On May 02, 2016, the petitioner executed two PPAs for each of the solar projects. The first 50 MW was commissioned on June 01, 2017, and the remaining 20 MW was commissioned on July 21, 2017. For the second project, the first 40 MW was commissioned on June 11, 2017, and the 30 MW was commissioned on August 11, 2017.
The generator, in its submission, noted that it was required to commence supply of power from the solar projects by the scheduled commissioning date, i.e., June 01, 2017. However, the commencement of supply was delayed due to the delay by the Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPNL) in providing transmission infrastructure for connectivity and power evacuation for the solar projects.
The solar generator submitted that NTPC had demanded an amount of ?70.6 million (~$950,701) on account of liquidated damages for the alleged delay in the commencement of power supply under the PPAs. NTPC failed to consider that delay in the commencement of supply was due to a delay in the availability of transmission and evacuation infrastructure.
The generator argued that NTPC had not suffered any loss or damage due to the delay in the commencement of supply from the solar projects. Further, NTPC was not entitled to collect the said amount as liquidated damages since the said amount was excessive and not a genuine pre-estimate of loss.
NTPC, in its reply, said that it was entitled to the payment of liquidated damages for the delay in commencement of supply of power and delay in making the contracted capacity available for dispatch by the scheduled commissioning date.
NTPC further added that the petitioner’s contention that no liquidated damages could be imposed if the delay in commissioning of the projects was due to delay related to transmission infrastructure was not valid.
Commission’s analysis
The Commission observed that the petitioner had submitted that the delay in commencement of supply from the 2×70 MW solar power projects at the Bhadla Solar Park Phase-II, Rajasthan, was due to the non-availability of transmission and evacuation infrastructure. As a result, the petitioner could commission the solar projects and commence supply of power only in parts, as and when adequate transmission and evacuation capacity was made available by RVPNL.
The Commission noted that the respondents had submitted that the delay in commissioning the projects did not fall within the scope and purview of the definition of force majeure as defined in the PPAs. Therefore, the petitioner was not entitled to any relief due to force majeure.
The central regulator stated that the solar generator had made it clear that for Project-1, 50 MW was commissioned on June 01, 2017 (no delay) while the remaining 20 MW was commissioned on July 21, 2017 (a delay of 50 days) and for Project-2, 40 MW was commissioned on June 11, 2017 (delay of 10 days) while the remaining 30 MW was commissioned on August 11, 2017 (a delay of 71 days). The Commission said that as the projects could be commissioned without the availability of connectivity, the request for an extension of the scheduled commissioning date could not be considered.
“However, given the existence of transmission constraint beyond the commissioning of the projects, the petitioner cannot be faulted for non-supply of power beyond the dates of commissioning of the projects. It is pertinent to mention here that NTPC has levied Liquidated damages until the commissioning of the projects only,” the Commission added.
Taking all the facts under consideration, the Commission noted that NTPC was entitled to recover liquidated damages as per the provisions of the PPA.
In April this year, CERC had directed Azure Power to file an affidavit, explaining the current developments leading to delay in commissioning the 1,200 MW of solar projects being developed in Rajasthan. Azure Power had approached CERC seeking a deadline extension from Power Grid Corporation of India Limited to lay the transmission lines.
Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable sector.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

China CORNEX signed cooperation agreement with the Italian Cestari Group

On November 13, CORNEX signed a strategic cooperation agreement with the Italian company Cestari Group in Wuhan, Hubei Province, China. According to the agreement,...

Solar Leader Enphase Energy Cutting 500 Jobs

California-based Enphase Energy, a company known for its solar power and electric vehicle (EV) charging technology, announced it is laying off about 500 workers....

Cincinnati’s solar array powers city operations, tens of thousands of homes

A sprawling solar array in Highland County now powers 20% of Cincinnati's operations and tens of thousands of homes. Cincinnati’s 900-acre solar farm was completed...

1.2-GW solar panel assembly facility to open in Puerto Rico

A contract solar panel assembly facility will soon open in Aguadilla, Puerto Rico, that will supply the utility-scale market on the island and hopefully...