CPSU Program for 12 GW of Solar Amended, VGF Capped at ₹5.5 Million

Solar projects must be commissioned within 30 months from the date of LoA

Source:MERCOM

The Ministry of New and Renewable Energy (MNRE) has issued amendments for setting up 12 GW of solar projects with viability gap funding (VGF) by central public sector undertakings (CPSUs) for self-use or use by government entities.
The total cost of the projects under this program is estimated to be ?480 billion (~$6.33 billion).
As per an earlier amendment, the Indian Renewable Energy Development Agency (IREDA) was made the implementing agency on behalf of the MNRE, including conducting the bidding through the VGF route.
Earlier this year, IREDA had floated a tender to set up 5 GW of grid-connected solar projects in India (Tranche III) under the CPSU program (Phase II). IREDA had capped the tariff under this tender at ?2.20 (~$0.030)/kWh. Following the announcement, Telecommunications Consultants India Limited (TCIL) issued an expression of interest to select partners for setting up solar projects under the program.
According to Mercom’s India Solar Tender Tracker, a total of 3.5 GW of solar tenders have been issued under the CPSU program.
The VGF is provided to cover the difference between the domestically produced solar cells and modules and those that are imported. As per the new amendment, the maximum permissible VGF has been kept at ?5.5 million (~$74,990)/MW, and the actual VGF will be decided through bidding. Earlier, the sum was 7 million (~$92,288)/MW.
As per the latest amendment, the power produced by the government entities can be used for self-use or use by government entities either directly or through distribution companies at the mutually agreed rate of 2.45 (~$0.033)/kWh. The rate would include all the charges, including wheeling and transmission charges, point of connection charges and losses, and cross-subsidy charges. Earlier, as per the existing clauses, the rate was fixed at 2.80 (~$0.037)/kWh.
The amendment further states that solar projects under this program will be commissioned within 30 months from the letter of award (LoA). The earlier time frame was 24 months from the date of LoA for projects up to 500 MW.
However, for projects over 500 MW, capacity up to 500 MW must be commissioned within 24 months from the date of LoA, and the remaining capacity must be commissioned within the next six months, MNRE has clarified.
Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Liu Zhuo, Sales Manager of TBEA, delivered a speech titled “Green Energy Makes Life Better” at COP16

On the afternoon of December 9, Liu Zhuo, Sales Manager for the Middle East Region at TBEA, delivered a speech titled "Green Energy Makes...

Side Event Themed “Solar empowers land and People from scarcity to prosperity:Integrated Solutions for water, food and ecosystems” took place at COP16

The side event of the 16th Conference of the Parties to the United Nations Convention to Combat Desertification (UNCCD) (COP16) "Solar empowers land and People from...

COP16 China Pavilion Side Event Series Report: Wang Weiying of China Renewable Energy Engineering Institute Proposed Coordinated Development of Renewable Energy and Ecology in...

The China Pavilion held a side event with the theme of "Planning and Ecological Design of Solar PV Power Stations in Desert Areas" on the...

Gao Sheng of Gaoming Technology said Solar greenhouses promote the development of agriculture in desertified area at COP16

The 16th Session of the Conference of the Parties to the United Nations Convention to Combat Desertification (UNCCD) (COP16) "Off-grid Solar Energy Empowers...