Vestas said it has received orders for a total of 139 MW for 77 V100-1.8 MW turbines from First Wind for two wind energy projects.
The 104.4 MW Palouse Wind project in Whitman County, Wash., will include 58 V100-1.8 MW turbines while the 34.2 MW Bull Hill wind power plant in Hancock County, Maine, will feature 19 V100-1.8 MW turbines.
The contracts for both projects include delivery and commissioning along with a 10-year service and maintenance agreement. Deliveries for Palouse Wind and Bull Hill are scheduled for mid-2012, and both projects are expected to be commissioned in late 2012.