Interconnection is broken: Radical rethinking is needed to achieve clean energy goals

We’re running out of time to transition our electric grid to clean energy sources at the pace needed to meet climate goals; it’s time to rethink the way states approach interconnection or it will kill our prospects.

Source:pv magazine

Significant progress has been made to decarbonize U.S. electricity, largely driven by impressive renewable energy growth. But one critical issue, left unaddressed, will almost certainly derail ambitious climate and clean energy goals: interconnection.

Interconnection policies determine how efficiently distributed energy resources (DERs), like solar and energy storage, can connect to the electric grid. The Interstate Renewable Energy Council (IREC) has participated in state-level regulatory processes to reform interconnection policies for DERs for over a decade, in over 35 states.

In that time, we’ve come to realize that without a radical rethinking of interconnection policies, it is highly unlikely that the U.S. will be able to deploy DERs at the speed and scale needed to meet bold climate goals.

Reaching a breaking point
Historically, there have typically been two or three state interconnection dockets active in a given year. Today, we are seeing a flood of interconnection dockets across the country, showing how this issue is already coming to a head.

Some states are opening interconnection dockets proactively, realizing reform will be needed to meet clean energy targets. For many others, it’s because the failures of current interconnection policies are becoming apparent as DER deployment grows.

Interconnection policies that were developed at a time of lower DER penetrations are failing in a number of areas, including interconnection timelines; compatibility with energy storage; distribution of grid upgrade costs; and lack of data accessibility.

Interconnection processes are often slow and cumbersome, and timeline accountability is hard to come by. When an excess of complaints about interconnection delays led Minnesota regulators to fine Xcel Energy $1 million in January, it was a rare victory for solar customers and project developers.

Beyond the need for accountability to reasonable timelines, interconnection policies need to move away from project-by-project approval toward a more streamlined approach. California is one state exploring expedited screening for certain types of projects.

Energy storage shortcomings
Another major shortcoming of most interconnection policies is how they deal with energy storage, which will be a critical component on a grid with high levels of renewables. Most interconnection policies do not recognize the unique characteristics of storage, and the process of interconnecting this technology remains complex and unclear in many states.

This will only become more of a blocker as storage deployment grows, with the impacts of FERC Order 2222 and Order 841 poised to further expand this market.
The allocation of grid upgrade costs is another area where significant interconnection reform will be needed to enable a future of high renewables. Currently, if upgrades are required to accommodate additional DERs on a circuit, the project that “triggers” the upgrades must pay the full cost.

These costs, often hundreds of thousands of dollars, can kill the economics of a project. This limits project development, delays needed infrastructure investments and leaves whole sections of the distribution grid closed to DER development. A few states, including Massachusetts and Maryland, are exploring new approaches to distribute upgrade costs across multiple projects and ratepayers and enable proactive grid investments.

Lack of access to grid data
Accessibility of data on grid conditions is another element of interconnection policies that needs reform. This data, such as which circuits have room for additional DER capacity, could significantly streamline the interconnection process. It could also allow developers to tailor projects to grid conditions—such as by choosing locations that don’t require upgrades, or proposing operating “schedules” to limit export to the grid at certain times.

making progress in this area and provide lessons for other states.

While interconnection reform is complex, solutions exist for each of these challenges. But commitment to holistic interconnection reform will be essential to achieving the change needed to reach high levels of renewables.

In subsequent articles in this series, IREC will delve into several of these issues, drawing from solutions developed in states around the nation.

Gwen Brown is communications director at the Interstate Renewable Energy Council. This article is part of a four-part series on interconnection reform. In the next article, we will explore why power control systems are essential to unlock the full value of energy storage on the grid and how interconnection policies must change to enable this. Subsequent articles will explore the need for greater accountability and data access and transparency in the interconnection process.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

China CORNEX signed cooperation agreement with the Italian Cestari Group

On November 13, CORNEX signed a strategic cooperation agreement with the Italian company Cestari Group in Wuhan, Hubei Province, China. According to the agreement,...

Solar Leader Enphase Energy Cutting 500 Jobs

California-based Enphase Energy, a company known for its solar power and electric vehicle (EV) charging technology, announced it is laying off about 500 workers....

Cincinnati’s solar array powers city operations, tens of thousands of homes

A sprawling solar array in Highland County now powers 20% of Cincinnati's operations and tens of thousands of homes. Cincinnati’s 900-acre solar farm was completed...

1.2-GW solar panel assembly facility to open in Puerto Rico

A contract solar panel assembly facility will soon open in Aguadilla, Puerto Rico, that will supply the utility-scale market on the island and hopefully...