Grid connection, lead times and costs main barriers to Hungarian wind power, but new government has


The time taken to connect wind farms to the grid, and the high costs of doing so, are the main barriers to wind energy development in Hungary, it was revealed today in Budapest at a workshop organised by the European Wind Energy Association (EWEA) and the Hungarian Wind Energy Association (HuWEA). Grid connection takes an average of 45 months in the country, and 10.6% of total project costs are spent on getting it. However, the new government is promising new plans to help reach the 2020 targets.


“Costs and long lead times are not the only problem,” said Jacopo Moccia, EWEA’s Regulatory Affairs Adviser. “Insufficient grid capacity and an unstable decision making process for granting building permits are also deterring investors. Things must change if Hungary is to reach its 2020 renewable energy target, and that will not be possible without a substantial contribution from wind energy.”


“Hungary needs to reach 13% renewable energy by 2020, and the new government is looking into how to exceed this target,” Péter Olajos, State Secretary for Energy and Climate Policy in the Ministry of National Economy told the workshop today. “Our aim is to create new jobs, reduce energy dependence on fossil fuels, and support rural development: renewables are one of the means to reach these goals.”


“In order to achieve the 2020 targets, 80% of investments must come from private investors. For this we need to create an attractive environment: resources, which we have, grids improvements, which we can do, and a regulatory framework, which the government intends to do.”


“It would be a matter of great pride for me if by the end of 2014 the government could announce that installed wind capacity is quadrupled”, added Olajos. 


At the end of 2009 Hungary had just above 200 MW of installed wind energy capacity. EWEA and HuWEA would like to see at least 1,200 MW installed in the country by 2020, which would provide about 5% of its electricity demand. 


Wind energy could provide up to 17% of EU electricity demand by 2020. This would avoid 333 million tonnes of CO₂ per year, equal to 29% of the EU’s greenhouse gas reduction target. Currently the wind industry employs 192,000 people in the EU; by 2020 this number is expected to grow to 446,000 jobs – 33 new jobs every week from now up to 2020. 

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Liu Zhuo, Sales Manager of TBEA, delivered a speech titled “Green Energy Makes Life Better” at COP16

On the afternoon of December 9, Liu Zhuo, Sales Manager for the Middle East Region at TBEA, delivered a speech titled "Green Energy Makes...

Side Event Themed “Solar empowers land and People from scarcity to prosperity:Integrated Solutions for water, food and ecosystems” took place at COP16

The side event of the 16th Conference of the Parties to the United Nations Convention to Combat Desertification (UNCCD) (COP16) "Solar empowers land and People from...

COP16 China Pavilion Side Event Series Report: Wang Weiying of China Renewable Energy Engineering Institute Proposed Coordinated Development of Renewable Energy and Ecology in...

The China Pavilion held a side event with the theme of "Planning and Ecological Design of Solar PV Power Stations in Desert Areas" on the...

Gao Sheng of Gaoming Technology said Solar greenhouses promote the development of agriculture in desertified area at COP16

The 16th Session of the Conference of the Parties to the United Nations Convention to Combat Desertification (UNCCD) (COP16) "Off-grid Solar Energy Empowers...