California Overwhelmed by 71 GW of Renewable Project Applications

Since putting itself on the market for renewables with its 33 percent renewable energy requirement, California has become like a wildly popular debutante, with a superfluity of suitors offering what Energy Prospects is calling a "glut" of renewable projects to meet the need.


Three times more would-be renewable energy projects are queueing to be added to the grid than would be needed, totaling 71 GW. Cal-ISO is having trouble fielding a truly staggering number of applications for renewable energy projects, enough to supply more than 100 percent of California's energy needs.


So far, the state has added 7.6 GW of renewable power in recent years, pretty much meeting the original Renewable Energy Standard set in 2006 to get 20 percent by 2010 (19 percent is installed, the full 20 percent is contracted for and will be online by 2013).


To meet the 33 percent target would take adding about another 20 GW. About 11 GW of wind and 7 GW of PV are almost surely in the pipeline, along with a gigawatt or two of geothermal and solar thermal.


For Cal-ISO, which finds room for all energy projects on the grid, the renewable "glut" is creating a problem: how seriously to take all of these suitors offering to meet California's clean energy requirement.


If all of the 71 to 73 GW of renewable energy were to make it through all the roadblocks of getting financing, passing environmental reviews and local NIMBY objections, then far more transmission would have to be built than Cal-ISO has estimated.


Modeling need based on all the generation in the queue could lead to an inflated estimate of costs to reinforce the transmission system. Not every project makes it. But if a too low number for their success rate were estimated, then all that potential clean energy would be not utilized.


Only the most serious contenders are counted. As evidence of the seriousness of their intentions, at least half a million dollars must be posted as interconnection financial security for a project, representing not only the renewable project developer's conviction that their project is going to be able to jump all the hurdles and get built, but also that they are willing to pay 15 percent of the cost to upgrade the grid to bring their energy to market.


And at $20,000 per megawatt in each project, these contenders are willing to pay over $7 million and much, much more for the privilege of helping add that grid infrastructure. What a problem for California to have, eh?

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Riyadh Declaration Solar Empowers Land and People Action Plan

December 9, 2024 Riyadh, Saudi Arabia On December 9, 2024, the 16th Conference of the Parties (COP16) of the United Nations Convention to Combat Desertification (UNCCD)...

Liu Zhuo, Sales Manager of TBEA, delivered a speech titled “Green Energy Makes Life Better” at COP16

On the afternoon of December 9, Liu Zhuo, Sales Manager for the Middle East Region at TBEA, delivered a speech titled "Green Energy Makes...

Side Event Themed “Solar empowers land and People from scarcity to prosperity:Integrated Solutions for water, food and ecosystems” took place at COP16

The side event of the 16th Conference of the Parties to the United Nations Convention to Combat Desertification (UNCCD) (COP16) "Solar empowers land and People from...

COP16 China Pavilion Side Event Series Report: Wang Weiying of China Renewable Energy Engineering Institute Proposed Coordinated Development of Renewable Energy and Ecology in...

The China Pavilion held a side event with the theme of "Planning and Ecological Design of Solar PV Power Stations in Desert Areas" on the...