A unit of China Energy Engineering Corp (HKG:3996) has secured a contract of some USD 500 million (EUR 457m) to design and install a 90-MW Photothermal and Photovoltaic Hybrid Power Station in Thailand.
China Gezhouba Group International Engineering Co Ltd got the engineering, procurement and construction (EPC) contract for the project in Changwat Khon Kaen. In addition to the solar facilities, it will also be in charge of the construction of a 2-km, 230-kV supporting transmission line.
The tentative contract term is of 30 months.