Home PV Companies PGCIL Acquires Ramgarh New Transmission to Facilitate 8.1 GW of Solar Power

PGCIL Acquires Ramgarh New Transmission to Facilitate 8.1 GW of Solar Power

The transmission system is to be completed within 18 months

Source:MERCOM

Power Grid Corporation of India Limited (PGCIL), a state-owned power transmission company, has acquired the Ramgarh New Transmission Limited (RNTL) under Phase II, Part-A of the ‘transmission strengthening program’ to evacuate 8.1 GW of power from solar energy zones in Rajasthan.
RNTL was incorporated on June 26, 2020, by REC Power Distribution Company Limited. In December 2020, REC invited bids for constructing the transmission network, and PGCIL had bagged this project along with two other power transmission projects through competitive bidding held in February 2021. PGCIL had emerged as the lowest bidder quoting a levelized tariff of ?390.53 million ($5.36 million) per year across 36 years.
After completing the bidding process, the special purpose vehicle was to be transferred to the selected bidder. The entity was acquired for about ?56.1 million (~$767,703), including 50,000 equity shares at par at ?10 (~$0.136) each, along with its assets and liabilities as of the acquisition date.
The project will be developed on a build, own, operate, and maintain basis.
The program’s Phase II includes evacuation of 1.05 GW of power in Bhadla complex, 2.2 GW in Fatehgarh complex, 1.9 GW in Ramgarh, and 2.95 GW in Bikaner.
As per the BSE filing, the transmission system comprises establishing a new 400/220kV substation at Ramgarh, 400kV DC transmission lines, and associated substation extension works, facilitating the transfer of power from renewable energy sources for onward disbursal to beneficiaries. The transmission system is an interstate transmission system (ISTS) and is to be completed within 18 months.
For the evacuation of power, a high capacity 765kV and 400kV transmission system interconnecting Bhadla-II, Fatehgarh-II, Sikar, and Khetri, along with the establishment of 765/400kV new substation at Sikar-II and Narela and 400/220kV new substation at Bikaner-II and Ramgarh-II have been planned under Phase II of the evacuation program.
Approval for grant of transmission license and adoption of transmission charges are to be obtained from the Central Electricity Regulatory Commission by RNTL after the acquisition by PGCIL.
In February this year, PGCIL bagged two power transmission projects in Rajasthan through tariff-based competitive bidding. These projects are being built to evacuate 8.1 GW of power from solar energy zones in the state.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Pexapark records 25 European PPAs for 790 MW in January

European developers signed 25 PPAs for 790 MW in January 2024, according to the latest report from Pexapark. The result is a 7% month-on-month decrease...

JinkoSolar gets 66.5MWh PV and energy storage project in Germany

JinkoSolar, a world-leading photovoltaic and energy storage company, announced today that it has successfully signed a German photovoltaic and energy storage project. The project...

RCT Power attends Intersolar North America & Energy Storage North America

In California, USA. Intersolar North America & Energy Storage North America 2025 was held at the San Diego Convention Center from February 25 to...

Shanghai Electric and Guangdong Energy Group signed cooperation agreement

On the morning of February 26, Shanghai Electric and Guangdong Energy Group officially signed a strategic cooperation agreement under the joint witness of Wu...