星期四, 21 11 月, 2024
Home PV Markets Puget Sound Energy to reach 63% clean energy by 2025

Puget Sound Energy to reach 63% clean energy by 2025

Source:pv-magazine

While approving the utility’s plan that would add 300 MW of utility-scale solar and 50 MW of storage by 2025, state regulators ordered the utility to increase the transparency of its resource planning and to advance equity for its customers.

Seattle-area utility Puget Sound Energy (PSE) will add 300 MW of utility-scale solar, 500 MW of wind, and 50 MW of battery capacity by 2025 to reach 63% clean generation.

PSE relies heavily on hydroelectric generation and now has 770 MW of wind capacity. Washington State has 600 MW of solar capacity, providing less than 1% of generation, according to the Solar Energy Industries Association (SEIA)。

The Washington Utilities and Transportation Commission (UTC) determined that the 63% renewables target, set by the utility in late 2021, appears “reasonable in light of forecasted costs.”

The UTC also said that PSE’s plans to add 80 MW of distributed solar and 25 MW of distributed battery storage by 2025 were reasonable. Regulators directed PSE to increase the amount of community solar in its plan, however, from 25 MW to 50 MW, saying that community solar “provides greater benefits to customers” than customer leasing of solar or battery resources.

PSE is Washington State’s largest utility, with 1.1 million electric customers.

Transparency

As a condition of approving the utility’s plan, state regulators required PSE to increase the transparency of its resource planning going forward. The UTC said that within 60 days PSE must provide a narrative describing the methodology used to develop its renewable energy targets, and how those targets will contribute to meeting the 63% clean energy target by 2025.

The UTC also required PSE to obtain a license for UTC staff to use the Aurora and PLEXOS models, which the utility uses in its planning. At least one other state, Arizona, requires transparent modeling for utility resource plans, allowing state regulators to reproduce a utility’s modeling, or modify it using different assumptions.

Regulators also required PSE to rerun its resource planning models with an updated methodology for incorporating the social cost of greenhouse gas emissions and updated capacity values for energy storage, saying that PSE had undervalued storage.

Based on those new model runs, regulators ordered PSE to recalculate its interim clean energy targets and its energy storage target, and to incorporate any changes in its 2023 resource plan.

Equity

Washington’s Clean Energy Transformation Act (CETA) requires the state’s utilities to transition to 80% clean electricity by 2030 and 100% clean electricity by 2045, and sets equity goals as well. The state’s three investor-owned electric utilities must file periodic plans to show how they will achieve those targets.

The UTC set numerous conditions for PSE to improve the equity aspects of its plan. For example, PSE was ordered to develop a rent-to-own option or other options in place of leasing rooftop solar and residential batteries to customers.

“Prioritizing the most impacted communities in an equitable distribution of benefits and reduction of burdens will make CETA implementation truly transformative,” said Mariel Thuraisingham, clean energy policy lead for the community coalition Front and Centered. “The UTC’s order is a major step to keep utilities on track and hold them accountable for a just transition to a clean energy future.”

Earthjustice, the environmental law nonprofit, represented Front and Centered and the nonprofit NW Energy Coalition in the UTC’s regulatory proceeding that reviewed PSE’s plan, with support from the consultancy GridLab.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

China CORNEX signed cooperation agreement with the Italian Cestari Group

On November 13, CORNEX signed a strategic cooperation agreement with the Italian company Cestari Group in Wuhan, Hubei Province, China. According to the agreement,...

Solar Leader Enphase Energy Cutting 500 Jobs

California-based Enphase Energy, a company known for its solar power and electric vehicle (EV) charging technology, announced it is laying off about 500 workers....

Cincinnati’s solar array powers city operations, tens of thousands of homes

A sprawling solar array in Highland County now powers 20% of Cincinnati's operations and tens of thousands of homes. Cincinnati’s 900-acre solar farm was completed...

1.2-GW solar panel assembly facility to open in Puerto Rico

A contract solar panel assembly facility will soon open in Aguadilla, Puerto Rico, that will supply the utility-scale market on the island and hopefully...