The Gujarat Electricity Regulatory Commission (GERC), in a recent order, approved the tariff of 2.64 (~$0.035)/kWh to procure power from a 100 MW solar project (PhaseX-R) being developed by SJVN Limited at the Raghanesda Solar Park in Gujarat.
The Commission directed the Gujarat Urja Vikas Nigam Limited (GUVNL) to sign the power purchase agreement (PPA) with the successful bidder. It also directed the petitioner to submit a copy of the PPA.
GUVNL filed a petition to adopt a tariff of 2.64 (~$0.035)/kWh discovered through a competitive bidding process.
Background
GUVNL conducted the tendering process in September 2018. Tariffs in the range of 2.84 (~$0.038)/kWh to 2.89 (~$0.039)/kWh were discovered in the e-reverse auction. The auction was later scrapped.
Later, GUVNL reissued the tender, after which 500 MW capacity was allocated while 200 MW remained unallocated due to undersubscription.
To auction the unallocated capacity, GUVNL issued a tender. In response, 100 MW capacity was allocated at a tariff of 2.65 (~$0.035)/kWh, and 100 MW capacity remained unallocated due to undersubscription.
GUVNL, for the fifth time, issued a tender to auction the remaining unallocated capacity of 100 MW.
SJVN was declared the winner in the reverse auction with a quoted tariff of 2.64 (~$0.035)/kWh for 100 MW capacity.
GUVNL, in its submission, said that the tariff of ?2.64 (~$0.035)/kWh, which included the impact of the Basic Customs Duty (BCD), was better than the tariff of 2.65 (~$0.035)/kWh-2.70 (~$0.036)/kWh at which 600 MW of projects had already been awarded.
The distribution company (DISCOM) added that the unique geographical conditions in the Raghanesda Solar Park and socio-economic parameters associated with its development needed to be considered.
The DISCOM added that it had received bids from three bidders for 100 MW, and two bidders had qualified for the e-reverse auction. In the reverse auction, SJVN was selected as the successful bidder.
Commission’s analysis
The Commission observed that GUVNL had initiated the bidding process to purchase 100 MW power from the solar power projects and had set a ceiling price as 2.73 (~$0.037)/kWh, which was subsequently revised to 2.65 (~$0.035)/kWh.
The state regulator noted that the DISCOM had made consistent attempts to invite bids for the entire 700 MW capacity. However, despite its best efforts, it could auction only for 600 MW.
The Commission added that in the earlier bidding process for 100 MW, the tariff discovered was 2.65 (~$0.035)/kWh. However, it was decided to undertake fresh bidding and tie up power at a lower tariff. Later, the discovered tariff was 2.64 (~$0.035)/kWh, taking into account the BCD with an estimated impact of about 0.40 (~$0.005)/kWh to 0.50 (~$0.006)/kWh.
Considering all the factors, the Commission decided to adopt the tariff of 2.64 (~$0.035)/kWh and asked GUVNL to sign the PPA with the successful bidder.
In March this year, the Appellate Tribunal for Electricity asked GUVNL to maintain the status quo in the scrapped 700 MW solar auction (Dholera Solar Park) until further orders. It said that the DISCOM could not proceed with the request for selection, nor could it open the technical and financial bids.
Earlier, the Commission had adopted a tariff of 1.99 (~$0.0270)/kWh discovered in the competitive bidding conducted by GUVNL for procuring power from 500 MW of grid-connected solar power projects in Gujarat.
Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.
Tariff of ₹2.64/kWh Approved for 100 MW of Solar Projects at Raghanesda Solar Park
The state regulator asked GUVNL to sign the PPA with the successful bidder
Source:MERCOM